Beagle 2: Lessons Learned

illustration only

Moffett Field CA (SPX) Aug 25, 2004
The Mars Express spacecraft, carrying the Beagle 2 lander, was launched on 2 June 2003, arriving in the vicinity of Mars in December. The separation of Beagle 2 from Mars Express occurred on 19 December. The satellite continued with its successful insertion into a Mars orbit on 25 December, the day on which Beagle 2 was due to land.

The Beagle 2 probe never was heard from again, despite a terrestrial radio telescope and orbital searches. The Beagle 2 team has issued their final report (297 pages), which is excerpted here for lessons learned in executing such a complex mission.

As the Executive Summary introduces, Beagle 2's loss to the astrobiology community is considerable: "Mars Express represented at its inception a unique opportunity for Europe to explore Mars.

The Beagle 2 probe was conceived to search for evidence of past and present life on the surface of the planet." The Mars Express orbiter continues to send back stunning high-resolution images as it maps the red planet for the coming years of its service life.

Beagle 2 [the UK led small lander on ESA's Mars Express] was flown successfully from launch through to ejection from Mars Express by a combined academic and industrial team. ...Beagle 2 failed to communicate after its entry, descent and landing of 25th December 2003. It is presumed to have failed during this critical mission phase.

The "lessons learned" apply to any potential reflight of a small lander like Beagle 2 and most if not all lander missions to Mars (and elsewhere in many cases), some however are very specific to a "Beagle 2" type design and relate to detailed design issues and lessons from testing etc. and some will strike the reader as very obvious (some perhaps only in hindsight).

This long list does not imply however that the design for Beagle 2 was inadequate but rather highlights the routes and ways to improve and make a small lander most robust and to ease the load on any future lander teams in terms of designers, integration and test teams and operations staff.

Beagle 2 was severely constrained by mass, volume and schedule and given adequate margins, time and resources many of these lessons would have been implemented on Beagle 2. We firmly believe that small Mars landers in the 60-130 kg class are possible given innovative design and engineering.

Beagle 2 was required to fit within a tightly constrained mass and volume limit. Consequently only very limited margins within the project were possible, forcing Beagle 2 to adopt innovative solutions to try and ensure a robust as possible probe design.

Beagle 2 was initially capped to a mass budget of 60kg ejected mass with a residual mass of 3kg remaining on Mars Express; when a formal request was made (August 2002) to increase this to 69 kg + 5kg no decision was taken by the project.

The Beagle 2 design team were always continually battling throughout the programme to control mass, not knowing whether it would be accepted for launch. The probe mass was eventually only accepted after delivery when it weighed 68.9 kg + 4.9 kg (March 2003).

Under the circumstances any other mass requests were impossible.

It is worth noting that the on-surface lander mass was very much as originally conceived, nearly all mass growth occurred in the EDLS, primarily due to the airbags/gasbags.

Given development, schedule and funding problems some key tests originally planned by the Beagle 2 team e.g. lander drop test, and pilot chute ejection and aeroshell release pyrotechnic-shock tests had to be deleted.

Priority was given to mission critical key developments, (main parachute, airbags/gasbags, electronics, software), and to the completion of the assembly and test programme.

Shock tests were carried out on Beagle 2 components however this was part of the formal mechanical qualification (a functional test before and after) and not under operational conditions.

The Beagle 2 team fully agree that more testing would have been valuable and would be keen to carry out such a future test programme with appropriate hardware to eliminate uncertainties in developing future lander systems.

The extremely high cost of a realistic test (and ultimately schedule limitations) was also a deciding factor.

Instead the main parachute was tested at low altitudes using coated fabric to simulate the effects of low pressures on Mars and via extensive mechanical load tests. The pilot chute has Huygens heritage.

Some aspects of the Huygens parachute system were tested at high altitude. US suppliers for critical components (in particular for the entry, descent and landing system) were selected by Beagle 2 to provide maximum use of existing world-wide expertise.

US International Traffic in Arms Regulations (ITAR) and Intellectual Property Rights (IPR) issues however prevented complete oversight of the probe design by the whole Beagle 2 team, particularly on issues relating to the EDLS, the airbags/gasbags, and their gassing system, the pilot parachute and its deployment device.

The Beagle 2 Airbags/Gasbags ILC Dover, who provided the airbags/gasbags for Beagle 2, produced the airbags for Pathfinder and the MER Missions; all these missions using airbags/gasbags have been successful.

The same manufacturing and materials technologies were employed for Beagle 2. The successful US technology was however developed for larger landers. Whilst the construction principles were retained for Beagle 2, the actual design is functionally unique and of mainly of UK origin.

After airbag/gasbag test failures, caused by design specification and development problems, the operational regime for the airbags/gasbags was revised by Astrium.

A delay in inflation was introduced to overcome concerns on leak rate and material chemical reaction with the inflation gas.

A reduced impact velocity was also defined, allowing a lower inflation pressure to avoid overpressurisation failure. Design detail remained unaffected and the need to introduce new technology or yet more mass growth was avoided.

Flight of the original design would have likely led to mission failure. These changes brought the airbag/gasbag operational scenario closer to that of Pathfinder and MER.

Further efforts to make the airbags/gasbags more robust required a large incremental change in mass and volume to accommodate an additional protection layer in the airbag/gasbag structure. This was not feasible within the mission constraints.

Beagle 2 acknowledges that the airbag/gasbag test programme was limited by access to and the cost of US test facilities (none were available in Europe). A series of ten tests were carried out with the airbag/gasbag design.

As tests were performed in each case the data from earlier tests were fed back into the programme; the final four tests, reflecting the revised operational scenario, were deemed successful.

ESA were provided with all the results but declined an opportunity to view film of the tests. More comprehensive testing could have been achieved with an earlier start to the programme.

The Entry, Descent and Landing (EDL) lessons learned are perhaps the most important, and this is the most risky part of the mission, and the time during the Beagle-2 mission that it probably failed.

Community
Email This Article
Comment On This Article

Related Links
Mars Express at ESA
SpaceDaily
Search SpaceDaily
Subscribe To SpaceDaily Express
Mars News and Information at MarsDaily.com
Lunar Dreams and more



Memory Foam Mattress Review
Newsletters :: SpaceDaily :: SpaceWar :: TerraDaily :: Energy Daily
XML Feeds :: Space News :: Earth News :: War News :: Solar Energy News


Spirit Heading To 'Home Plate'
Pasadena CA (JPL) Jan 09, 2006
Last week Spirit completed robotic-arm work on "El Dorado." The rover used all three of its spectrometers plus the microscopic imager for readings over the New Year's weekend.









  • NASA plans to send new robot to Jupiter
  • Los Alamos Hopes To Lead New Era Of Nuclear Space Tranportion With Jovian Mission
  • Boeing Selects Leader for Nuclear Space Systems Program
  • Boeing-Led Team to Study Nuclear-Powered Space Systems

  • Apollo's Lunar Leftovers
  • New Moon Shot Not So Costly
  • Armstrong Reflects On A New Visions For Space Exploration
  • Sunny lunar mountain good site for base

  • Aerospace Industry Employment Increases After Falling To 50-Year Low
  • US Working To Resume Space Shuttle Flights In March
  • NASA Working On Early Version Of Star-Trek-like Main Ship Computer
  • Space Research Highlighted In Next EU Framework Program

  • SWAP To Determine Where The Sun And Ice Worlds Meet
  • Hubble Fails To Spot Suspected Sedna Moon
  • Life Beneath The Ice In The Outer Solar System?
  • Gravity Rules: The Nature of Planethood

  • Scientists Discover Ganymede Has A Lumpy Interior
  • Link Discovered Between Earth's Ocean Currents And Jupiter's Bands
  • Researchers Show Io Vaporizing Rock Gases Into Atmosphere



  • Cassini-Huygens Periapsis Raising Manoeuvre
  • Shepherding The Lightweight World
  • Cassini On Course For Titan Flyby
  • Ultraviolet South Pole

  • Space Houses On Earth
  • Navy Researchers Test Polymers To Help Fuel Tanks 'Heal' When Shot
  • Nonexistent Strategy Leaves US Specialty Metals Industry At Risk
  • Light-Activated Glue Holds And Releases Workpieces In A Flash

  • The content herein, unless otherwise known to be public domain, are Copyright 1995-2006 - SpaceDaily.AFP and UPI Wire Stories are copyright Agence France-Presse and United Press International. ESA PortalReports are copyright European Space Agency. All NASA sourced material is public domain. Additionalcopyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement,agreement or approval of any opinions, statements or information provided by SpaceDaily on any Web page published or hosted by SpaceDaily. Privacy Statement